 |
 |
December 2006
December aerial views show the park close to completion, as SAM staff prepares for the opening events scheduled to start in early January. |
 |
 |
November 2006
Construction photography for this month highlights the installation of Pedro Reyes' Capulas and his 130-foot Evolving City Wall Mural. |
 |
 |
October 2006
The park comes alive with sculpture, as major works such as Alexander Calder's The Eagle, continue to be installed. |

|
 |
September 2006
Roxy Paine's Split and Claes Oldenburg and Coosje van Bruggen’s Typewriter Eraser, Scale X were installed this month. |

|
 |
August 2006
This month many of the park precincts will achieve their final grades, as the topsoil and irrigation is placed in preparation for planting in the final months. |
 |
 |
July 2006
Preparations were made for the first major art installation that occurred at the end of the month. |
 |
 |
June 2006
The steel for the Burlington Northern Pedestrian Bridge was placed by the end of the month, connecting all three parcels of the park. |
 |
 |
May 2006
Construction was active in all parcels of the park, with the framing and siding of the PACCAR Pavilion, plantings in the grove, and beginning preparations for art installation. |
 |
 |
April 2006
Weather permitting, the park will start to take on a whole new "green" look this month! |
 |
 |
March 2006
The placement of the PACCAR Pavilion’s structural steel was completed in the month of March, as were the forming and pouring of the structural concrete walls. |
 |
 |
February 2006
The construction team completed the seawall stabilization and beach excavation within the “fish window” (the winter period that is least disruptive for sensitive salmon habitat and migration). |
 |
 |
January 2006
January saw a blur of construction activity on all three parcels—from Western Avenue to the water’s edge. |
 |
 |
December 2005
As we move into the winter months, activity will increase on the waterfront as the seawall stabilization and pocket beach excavation get underway. |
 |
 |
November 2005
In November construction continued on all three parcels and the remediation of the waterfront was completed. |
 |
 |
October 2005
A relatively dry autumn allowed for unimpeded construction activity through the fall months. |
 |
 |
September 2005
Earthwork is a major component of the construction activity. By the end of the park’s construction, over 200,000 cubic yards of fill will have been brought to the site. |
 |
 |
August 2005
Construction activity commenced in early August with the demolition of the remaining foundations of the former UNOCAL building on the corner of Broad Street and Western Avenue. |
 |
 |
July 2005
When the new Olympic Sculpture Park opens in the winter of 2006, it will transform a major industrial site into an 9-acre park that will be free and accessible to the public. |
| |